Start Date: On or about Tuesday, March 5, 2024 (Weather Permitting)
Contract Time: 180 Calendar Days (Weather Permitting)
Limits: East Linden Avenue (CR-700) to Gibbsboro road (CR-686), Borough of Lindenwold, New Jersey
Project Highlights:
- Full Depth Reclamation (FDR) of the existing roadway, with a 2” HMA 19.5M64 Base Course and 2” HMA 9.5M64 Surface Course Overlay
- Concrete Curb, Curb Ramps, Concrete Sidewalk (If & where directed) , Monolithic Concrete Curb and Gutter & Reset Castings,
- Inlets and Manholes, Reconstruct Inlets, Installation of Type Double B Inlets, Reinforced Concrete Storm Pipe, Ductile Iron Storm Pipe, Raised Pavement Markers, Traffic Striping
Total Estimated Costs: $2,041,000.00
Any Questions Contact: Mathew Kearney Project Manager, of French & Parrello Associates, at 732.673.2184 and/or Vibhuti Bhimani, Assistant County Engineer, Camden County Division of Engineering at 856.566.2938
Weekly Progress Reports:
March 29, 2024
April 5, 2024
April 12, 2024
April 19, 2024
April 26, 2024
May 3, 2024
May 10, 2024
May 17, 2024
May 24, 2024
May 31, 2024
June 7, 2024
June 14, 2024
July 5, 2024