Improvements to Kings Highway (CR-551S) from Market Street (CR-634) to Hopkins Road (CR-647)

Please visit our project website (www.kingshighwaycc.com) for real-time project updates and announcements. Information on daily work zones, detours, and closures will be available. The project website will also have instructions on signing up for e-mail notifications and alerts throughout construction.

 

Name of Project:  Improvements to Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

Start Date: Tentatively, Monday, September 16, 2024

Contract Time: Substantial completion = 340 calendar days

Final completion = 380 calendar days

Limits: Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

Project Highlights:

  •  Milling and/or removal of existing concrete pavement and installation of hot-mix asphalt pavement
  • Resurfacing from Market Street (CR-634) to Hillside Avenue (CR-661)
  • Full-depth reconstruction from Hillside Avenue (CR-661) to West
    Atlantic Avenue (CR-727)
  •  Resurfacing from West Atlantic Avenue (CR-727) to Hopkins Road
  •  Improvements and rehabilitation to existing storm sewer system
  •  Cleaning and lining of existing sanitary sewer system and lateral replacement
  •  Concrete vertical curb, sidewalk, and ADA-accessible curb ramps
  •  Traffic striping, signage, and raised pavement markers

Total Estimated Cost: $10,745,085.83

Contractor: South State, Inc.

Questions? Contact:
Paul Nolan, Project Manager, Colliers Engineering & Design, (732) 704 – 5931
James Winckowski, Camden County Engineer, (856) 382 – 2699
Kyle Ebersole, Assistant Camden County Engineer, (856) 566 – 2980 ext. 42968


Weekly Progress Reports: