Project Schedule:
- Bid Opening Date: Tuesday, June 29th, 2021
- Notice to Proceed: Wednesday, November 3rd, 2021
- Start Date: Wednesday, November 10th, 2021
- Change Order #1 Date: June 23, 2022
- Substantial Completion Date: Friday. September 23rd, 2022
- Stop Work: Notice 8/26/2022: Effective Date 8/15/2022
- Amended NTP: N/A
- Final Completion Date: Thursday, October 13th, 2022
- Initial Award: $2,403,571.3
Contract 1:
- Road Work Alert
- November 12, 2021
- November 19, 2021
- November 26, 2021
- December 3, 2021
- December 10, 2021
- December 17, 2021
- December 24, 2021
- December 31, 2021
- January 7, 2022
- March 25, 2022
- April 1, 2022
- April 8, 2022
- April 15, 2022
- April 22, 2022
- April 29, 2022
- May 6, 2022
- May 13, 2022
- May 20, 2022
- May 27, 2022
- June 3, 2022
- June 10, 2022
- June 17, 2022
- June 24, 2022
- June 27, 2022
- July 8, 2022
- July 15, 2022
- July 22, 2022
- July 29, 2022
- August 5, 2022
- August 12, 2022
- August 19, 2022
- August 26, 2022
- September 2, 2022
- September 9, 2022
- January 13, 2023
- February 3, 2023
- February 10, 2023
- February 17, 2023
- February 24, 2023
- June 16, 2023
- June 23, 2023
- June 30, 2023
- July 7, 2023