Station Avenue (CR 656) and Haddon Lake Park Roadway Improvements Phase 1

START DATE: Spring 2023

TIMELINE: 336 Calendar Days (Weather Permitting)

LIMITS: Station Avenue (Second All caps line in yellow box) (CR 656) – 

  • White Horse Pike (NJSH 30) to Vicinity of E. Atlantic (CR 727) 
  • 9th Avenue (CR 653) to Intersection of 10th Avenue (CR 655)/S. Park (CR 661)
    • South Park (CR 661) – vicinity of Bellmawr Avenue to vicinity of Hillside Avenue (CR 661) and Prospect Ridge (CR 654)
    • Glover Avenue (CR 661B) – between S. Park (CR 661) and vicinity of N. Park (CR 661A)
  • Hillside Avenue (CR 661) – from S. Park (CR 661) to Kings Highway (CR 551S)
  • 13th Avenue – S. Park (CR 661) to Kings Highway (CR 551S) (Sylvan Avenue to Kings Highway(CR 551S) under Municipal jurisdiction – to be milled and repaved under SSA)

PROJECT HIGHLIGHTS:

  • Drainage and roadway improvements
  • handicap ramps
  • concrete vertical curb (where applicable)
  • HMA walking path improvements
  • geometric intersection improvements
  • striping and signage and tree plantings

TOTAL PROJECT COST: $3,878,800.00

ANY QUESTIONS CONTACT:

Camden County Public Works 24 Hour Hotline at 856.566.2980