Berlin-Cross Keys Road Improvement (CR 689):
Contract 1 (Completed June 2020)
- November 8, 2019
- November 15, 2019
- November 22, 2019
- November 29, 2019
- December 6, 2019
- December 14, 2019
- December 20, 2019
- December 27. 2019
- January 3, 2020
- January 10, 2020
- January 17, 2020
- January 24, 2020
- April 24, 2020
- May 1, 2020
- May 8, 2020
- May 15, 2020
- May 22, 2020
- May 22, 2020
- May 29, 2020
- June 1, 2020
Contract 2 (In-Progress)
- Road Work Alert
- January 29, 2021
- February 19, 2021
- March 5, 2021
- March 26, 2021
- April 2, 2021
- April 9, 2021
- April 16, 2021
- April 23, 2021
- April 30, 2021
- May 7, 2021
- May 14, 2021
- May 28, 2021
- June 4, 2021
- June 11, 2021
- June 18, 2021
- June 25, 2021
- July 2, 2021
- July 9, 2021
- July 16, 2021
- July 23, 2021
- July 30, 2021
- August 6, 2021
- August 13, 2021
- August 20, 2021
- August 27, 2021
- September 3, 2021
- September 10, 2021
- September 17, 2021
- September 24, 2021
- October 1, 2021
- October 8, 2021
- October 15, 2021
- October 22, 2021
- October 28, 2021
- November 5, 2021
- November 12, 2021
Contract 3
Bid Opening Date: June 2, 2022
Notice to Proceed: August 23, 2022
Start Date: September 6, 2022
Substantial Completion Date: July 24, 2023
Final Completion Date: August 23, 2023
Initial Award: $6,946,586.14 July 16, 2022