County Current Projects

In order to keep Camden County residents informed on major roadwork and infrastructure projects, the Camden County Board of  Commissioners is posting the County’s Department of Public Works progress reports, with photos. Through these reports from our engineers and the construction company doing each job, residents can see the progress step-by-step. Click on the link under each project to view the weekly reports”

For questions about Public Works projects, call (856) 566-2980.

Berlin-Cross Keys Road Improvement (CR 689):

Contract 1 (Completed)
Contract 2 (Completed)

Contract 3 (In-Progress)

  • Bid Opening Date: June 2, 2022
  • Notice to Proceed: August 23, 2022
  • Start Date: September 6, 2022
  • Substantial Completion Date: July 24, 2023
  • Final Completion Date: August 23, 2023
  • Initial Award: $6,946,586.14 July 16, 2022

Contract 4

Click for Weekly Progress Reports

 

]

 

(CR 621) Roadway Improvements along Park Avenue from Union Avenue (CR 615) to Cove Rd (CR 616) in Pennsauken Township

Start Date: April 25, 2022

Click for Weekly Progress Reports

Roadway Improvements along Blackwood-Clementon Road (CR 534) – from Little Gloucester Road (CR 759) to College Drive in Gloucester Township.

  • NTP: 8/1/22
  • Substantial Completion:  10/30/22
  • Final completion : 11/29/22
  • Initial award:  $1,939,000 5/19/22

Click for Weekly Progress Reports

Evesham Road (CR544) from the Vicinity of US Route 30 to Burnt Mill Road

Click here for Weekly Progress Reports

  • Start Date: 11/3/21
Roadway Improvements along Sicklerville Road (CR 681) – from Chews Landing Road (CR 704) to Cross Keys Road (CR 689) in Winslow Township.

  • Bid Opening: March 1, 2022
  • NTP: July 11, 2022
  • Start Date: July 11, 2022
  • Substantial Completion Date: December 8, 2022 (150 Calendar Days)
  • Stop Work: N/A
  • Amended NTP: N/A
  • Final Completion Date: January 7, 2023 (180 Calendar Days)
  • Initial Award $2,246,405.60

Click for Weekly Progress Reports

Roadway Improvements along Almonesson Road (CR 706) –  from NJSH 168 to County line in Gloucester Township.

  • Initial award $1,155,076:  2/17/22
  • NTP: 9/13/22
  • Substantial completion: 2/10/23
  • Final completion: 4/30/23

Click for Weekly Progress Reports

Roadway Improvements along Union Avenue (CR 615) – from Maple Avenue to Park Avenue in the Township of Pennsauken.

  • Bid Opening March 31, 2022
  • NTP: 6/22/22
  • Start Date: 6/22/22
  • Substantial Completion Date: pending
  • Final Completion Date: 12/18/22
  • Initial Award $4,200,000

Click for Weekly Progress Reports

 

West of the White Horse Pike Roadway Improvements (CR 544) – along Evesham Road from Hartford Avenue (CR 736) to Charles Avenue in Gloucester Township, Runnemede Borough, and Magnolia Borough.

  • NTP:  May 16, 2022
  • Substantial Completion:  Nov. 12, 2022
  • Final Completion:  Dec 12, 2022
  • Initial Award $1,779,113

Click for Weekly Progress Reports

 

East of the White Horse Pike Roadway Improvements (CR 544) Along Evesham Road from US Route 30 to Burnt Mill Road in Magnolia Borough, Lawnside Borough, Somerdale Borough, Cherry Hill Township and Voorhees Township.

  • Initial award: $2,403,571 7/22/21
  • NTP:  3/1/22
  • Substantial completion: date pending

Church Road, Cherry Hill (CR 616)

  • Awarded – April 21, 2022
  • Partial NTP – November 14, 2022
  • Amended NTP – February 7, 2023
  • 2nd Amended NTP – March 27, 2023
  • Substantial Completion – December 1, 2023
  • Final Completion – December 31, 2023
  • Initial Award – $4,200,000

Click for Weekly Progress Reports

Greentree Road (CR 674) From Route 70 to Burlington County Line in Cherry Hill.

  • Initial award: $3,107,848 5/19/22
  • NTP: 10/17/22
  • Substantial completion: 8/18/23
  • Final completion: 10/17/23
Replacement of Somerdale Road Bridge (CR 677), Gloucester Township

  • Initial award:  $4,123,485
  • NTP: pending
  • Substantial completion: pending
  • Final completion: pending

Burnt Mill Road (CR 670) Roadway Improvements

  • Bid Opening Date: June 21, 2022
  • Notice to Proceed Date: February 2, 2023
  • Start Date: February 27, 2023
  • Anticipated Completion Date: June 30, 2023
  • Contract Completion Date: August 1, 2023
  • Contract Completion Percentage: 3.96%

Click for Weekly Progress Report