County Completed Projects

2021

 

Lower Landing / Good Intent Road (CR 681)

 

 

Pennington/Chew Rd CR 536 – Rt 30 to Pestleton Road – Waterford & Winslow

Haddonfield-Sorrel House Road (Cr 644) – Pennsauken

Haddonfield-Sorrel House Road (Cr 644) – Pennsauken

Bid Opening Date: 8/7/2020
Notice to Proceed: 11/9/2020
Start Date: 11/9/2020
Substantial Completion Date: 8/26/2021
Final Completion Date: 9/16/21
Initial Award: $1,938,370.80

 

East Taunton Road (CR 536)

Bid Opening Date: 1/22/2021
Notice to Proceed: 4/29/2021
Start Date: 4/29/2021
Substantial Completion Date: 8/172021
Final Completion Date: 9/26/2021
Initial Award: $1,227,895.21

Roadway Safety Improvements, Evesham Road (Cr 544) Guide Rail, Various Municipalities

Bid Opening Date: 3/19/2019
Notice to Proceed: 9/15/2019
Start Date: 9/11/2019
Substantial Completion Date: 1/3/2020
Stop Work: 1/17/2020
Amended NTP: 6/1/2021
Final Completion Date: 8/15/2021
Initial Award: $524,410.00

Atlantic Avenue Pedestrian Improvements, Broadway (CR 551) and South 8th Street, Camden

Bid Opening Date: 4/29/2021
Notice to Proceed: 6/30/2021
Start Date: 7/5/2021
Substantial Completion Date 9/11/202
Final Completion Date: 10/2/2021
Initial Award: $202,150.76

 

2020

 

Chapel Avenue, Cherry Hill

  • Bid Opening Date: 7/30/2019
  • Notice to Proceed: 9/20/2019
  • Start Date: 10/14/2019
  • Initial Completion Date: 10/13/2020
  • Substantial Completion Date: 9/12/2020
  • Final Completion Date: 3/11/2021
  • Initial Award: $3,729,499.85

 

Kresson Road (CR 671) – Cherry Hill Township

  • Bid Opening Date: 3/6/2020
  • Notice to Proceed: 5/11/2020
  • Start Date: 5/26/2020
  • Initial Completion Date: 8/24/2020
  • Final Completion Date: 10/18/2020
  • Initial Award: $1,510,503.00

 

Hinchman Ave (CR 657) – Homestead Ave to Chews Landing Road – Haddonfield

  • Bid Opening Date: 6/30/2020
  • Notice to Proceed: 8/19/2020
  • Start Date: 9/14/2020
  • Initial Completion Date: 1/12/2021
  • Final Completion Date: 2/1/2021
  • Initial Award: $2,301,249.14

 

Blue Anchor Road – Winslow Township

Woodcrest Road (Cr 667) Bridge over PATCO

  • Bid Opening Date: 7/30/2020
  • Notice to Proceed: 10/20/2020
  • Start Date: 10/27/2020
  • Initial Completion Date: 12/6/2020
  • Final Completion Date: 12/26/2020
  • Initial Award: $730,616.96

Haddonfield Berlin CR 561 Phase 1, Evesham Rd to Kresson Rd, Cherry Hill

 

Jarvis Road, Gloucester Township (CR 687)

Westfield Ave Phase 2, Pennsauken Township

Peter-Cheeseman Road from Hickstown Road to Erial Road in Gloucester Township

Signal at Kearsley & Berlin-Cross Keys Rd

 

North Park Drive – Berlin

Watsontown New Freedom, Rt 30 to Cross Keys

Berlin – Cross Keys Road CR 689, Phase 1

2019

 

Lake Blvd, Lindenwold

Hampton Road, Cherry Hill

Improvements to Avondale and Breslin Avenue, Haddon Township

Replacement of Clementon Berlin Road Bridge in the Borough of Clementon

Intersection Improvements: E. Taunton Road and Route 73 Ramp

2018

 

Coles Avenue, Cherry Hill Township

Federal Street (CR 537) between 19th and Marlton Pike in the City of Camden

Grove Street & Cuthbert Blvd Bridges

Warwick Road, Boroughs of Somerdale, Hi-Nella & Stratford

Haddon Avenue Gateway

East Atlantic Avenue Bridge

Erial-Clementon Road Project, Gloucester Township

Westfield Ave. Phase 1,
Pennsauken Township

  •  

Jackson Road Reconstruction,
Waterford Township